Procurement: purchase order → goods receipt → bill
| Level | Duration | Prerequisites | For | Needs |
|---|---|---|---|---|
| Intermediate | 90 min | B04, B05, B09 | Procurement officers, storekeepers, bookkeepers | Procurement + Inventory |
Learning objectives
- Raise and approve a purchase order (PO).
- Receive the goods (fully or partly) with a goods receipt (GR) that puts them in stock.
- Match the supplier's bill to the PO and the GR (three-way match).
- Handle short deliveries, over-billing and returns with a debit note.
- Use the Procurement Dashboard to follow late orders.
Key ideas
Three-way match: before you pay, three documents must agree:
What we ORDERED (PO) = What ARRIVED (GR) = What we are BILLED (bill)
This is the strongest protection against paying for goods you never received.
| Document | Accounting effect |
|---|---|
| Purchase order | None: it is a commitment |
| Goods receipt | Stock goes up (quantity and value) |
| Bill | The payable to the supplier is recorded |
| Debit note | Reduces what you owe (returns, overcharges) |
Where to go
Procurement › Procurement Dashboard · Purchase Orders · Goods Receipt · Bills · Payments · Debit Note, or + Create › Purchase.
Step by step
1. Raise the PO
- + Create › Purchase (or Procurement › Purchase Orders › New).
- Choose the supplier, give a title and a delivery date, and a delivery address if needed.
- Add lines: item, quantity, agreed unit cost. Units of measure work here, so you can order 10 crates of 12.
- Attach the supplier's proforma if you have one.
- Submit, then Approve (per your approval rules).
- Send the PO PDF to the supplier.
2. Receive the goods
- When the delivery arrives, open Procurement › Goods Receipt › New and pick the PO (or click Receive on the PO).
- The PO lines fill in. Enter the quantity actually received per line. Partial deliveries are fine; the rest stays open on the PO.
- For perishables, enter the batch/lot and expiry date (lesson I03).
- Choose the warehouse or branch the goods go into.
- Attach the delivery note and confirm. The stock goes up now.
3. Record the bill against the PO
- When the supplier's invoice arrives, create the bill from the PO (or link it to the PO).
- Solafide compares ordered, received and billed quantities and prices and flags any difference.
- If it matches, approve the bill and schedule the payment (lesson B09).
4. When things don't match
| Situation | Action |
|---|---|
| Fewer goods arrived than ordered | Receive what arrived; wait for the rest, or close the PO line |
| The supplier billed more than received | Don't approve. Ask for a corrected invoice, or approve the correct quantity and raise a debit note. |
| Goods were damaged and sent back | Stock Transaction › Supplier Return (Out) plus a Debit Note |
| The price is higher than on the PO | Get approval, or dispute it with the supplier |
5. Follow up
The Procurement Dashboard shows open POs, Late POs (past the delivery date), goods waiting to be billed and bills waiting to be paid.
What happens in the accounts
| Event | Debit | Credit |
|---|---|---|
| GR: 1 crocodile, 50 000 | 32 Raw materials stock 50 000 | 401 Supplier (or GR clearing) 50 000 |
| Bill approved (matches the GR) | clears the clearing account / VAT 445x if any | 401 Supplier |
| Payment | 401 Supplier | 52 / 57 / 552 |
Common mistakes
| Mistake | Fix |
|---|---|
| Creating the bill without linking the PO | No match check. Always bill from the PO. |
| Receiving the full PO when half arrived | Stock overstated. Receive only what you count. |
| Buying outside the PO process "because it's urgent" | Use a requisition (I05) or an expense payment, never an untracked purchase |
Practice exercise
PO to Marché Mokolo Wholesale: 1 crocodile (production material) at 50 000 and 5 kg of spices at 2 000/kg. Only 4 kg of spices arrive. Receive them, bill the supplier (they bill 5 kg), spot the mismatch and resolve it.
Check your understanding
- Which document makes the stock go up?
- What are the three documents in a three-way match?
- The supplier sends back nothing but bills 10 % too much. Which document reduces what you owe?
- The goods receipt.
- Purchase order, goods receipt, supplier bill.
- A debit note (or ask for a corrected invoice before approving).